Alabama mechanics lien deadlines

2 deadlines NoticeGuard models for Alabama: what each one counts from, the statute it was read from, and the statute text.

Information, not legal advice. This app reports what the statute says and cites the section it read. It is not legal advice, it does not file anything for you, and it does not tell you what to do.
Verify with the statute or an attorney. Statutes change, and courts reinterpret them. Every deadline in this app comes from a statute read on the date shown next to its citation - that snapshot can go out of date. Missing a mechanics lien deadline can extinguish your claim permanently, so confirm any deadline you are relying on with an attorney licensed in that state before you act on it.
Data verified: statute text retrieved 2026-09-21 (each citation below carries its own date). Rule data from the NoticeGuard app, source commit 22f9300.

Deadlines at a glance

DeadlineCounted fromApplies toStatute
File verified statement of lien (original contractor)180 days after last furnishing (last day on site)Original contractorCode of Alabama § 35-11-215 (sole operative sentence)
File verified statement of lien (subcontractor, supplier, or preconstruction service provider)120 days after last furnishing (last day on site)Subcontractor, Supplier, Preconstruction serviceCode of Alabama § 35-11-215 (sole operative sentence)

Work out a date for Alabama with the calculator

Each deadline, with the statute

File verified statement of lien (original contractor)

Filed in the office of the judge of probate, counted from this claimant's own last item of work, labor, or material furnished.

What it counts from. 180 days after last furnishing (last day on site).

Applies to. Original contractor.

Code of Alabama § 35-11-215 (sole operative sentence)
Official source · statute text retrieved 2026-09-21

“The lien declared in this division shall be deemed lost unless the statement referred to in Section 35-11-213 shall be filed by every original contractor within six months and by every journeyman and day laborer within 30 days, and by every other person entitled to such lien within four months, after the last item of work or labor has been performed or the last item of any material, fixture, engine, boiler, or machinery has been furnished for any building or improvement on land or for repairing, altering, or beautifying the same under or by virtue of any contract with the owner or proprietor thereof, or his agent, architect, trustee, contractor, or subcontractor.”

If the date is missed (the statute's own terms). The statute's own mechanism: "The lien declared in this division shall be deemed lost" unless filed within the stated period.

Also stated next to this deadline.

File verified statement of lien (subcontractor, supplier, or preconstruction service provider)

Filed in the office of the judge of probate, counted from this claimant's own last item of work, labor, or material furnished.

What it counts from. 120 days after last furnishing (last day on site).

Applies to. Subcontractor, Supplier, Preconstruction service.

Code of Alabama § 35-11-215 (sole operative sentence)
Official source · statute text retrieved 2026-09-21

“The lien declared in this division shall be deemed lost unless the statement referred to in Section 35-11-213 shall be filed by every original contractor within six months and by every journeyman and day laborer within 30 days, and by every other person entitled to such lien within four months, after the last item of work or labor has been performed or the last item of any material, fixture, engine, boiler, or machinery has been furnished for any building or improvement on land or for repairing, altering, or beautifying the same under or by virtue of any contract with the owner or proprietor thereof, or his agent, architect, trustee, contractor, or subcontractor.”

If the date is missed (the statute's own terms). The statute's own mechanism: "The lien declared in this division shall be deemed lost" unless filed within the stated period.

Also stated next to this deadline.

Weekend and holiday rollover

NoticeGuard does not model a weekend or holiday extension for Alabama. The dates above are the plain count from the date you enter. Check whether a Saturday, Sunday or holiday changes your date.