Nebraska mechanics lien deadlines

3 deadlines NoticeGuard models for Nebraska: what each one counts from, the statute it was read from, and the statute text.

Information, not legal advice. This app reports what the statute says and cites the section it read. It is not legal advice, it does not file anything for you, and it does not tell you what to do.
Verify with the statute or an attorney. Statutes change, and courts reinterpret them. Every deadline in this app comes from a statute read on the date shown next to its citation - that snapshot can go out of date. Missing a mechanics lien deadline can extinguish your claim permanently, so confirm any deadline you are relying on with an attorney licensed in that state before you act on it.
Data verified: statute text retrieved 2026-09-21 (each citation below carries its own date). Rule data from the NoticeGuard app, source commit 22f9300.

Deadlines at a glance

DeadlineCounted fromApplies toStatute
Record construction lien120 days after last furnishing (last day on site)Original contractor, Subcontractor, Supplier, Preconstruction serviceNebraska Revised Statute § 52-137 (1)
Send copy of recorded lien to owner10 days after notice of construction lien recordedOriginal contractor, Subcontractor, Supplier, Preconstruction serviceNebraska Revised Statute § 52-135 (3)
Institute judicial proceedings to enforce the lien730 days after notice of construction lien recordedOriginal contractor, Subcontractor, Supplier, Preconstruction serviceNebraska Revised Statute § 52-140 (1)

Work out a date for Nebraska with the calculator

Each deadline, with the statute

Record construction lien

Recorded with the register of deeds, counted from this claimant's own final furnishing of services or materials.

What it counts from. 120 days after last furnishing (last day on site).

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

Nebraska Revised Statute § 52-137 (1)
Official source · statute text retrieved 2026-09-21

“A claimant's lien does not attach and may not be enforced unless, after entering into the contract under which the lien arises and not later than one hundred twenty days after his or her final furnishing of services or materials, he or she has recorded a lien.”

If the date is missed (the statute's own terms). The statute's own mechanism: the lien "does not attach and may not be enforced unless" recorded within this period.

Also stated next to this deadline.

Send copy of recorded lien to owner

A copy of the recorded lien, sent to the contracting owner, counted from the date the lien was recorded.

What it counts from. 10 days after notice of construction lien recorded.

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

Nebraska Revised Statute § 52-135 (3)
Official source · statute text retrieved 2026-09-21

“The claimant shall send a copy of a recorded lien to the contracting owner within ten days after recording, and the recording shall be within the time specified for the filing of liens under section 52-137.”

If the date is missed (the statute's own terms). The statute states this as a duty ("shall send") alongside the recording deadline itself, rather than a separately stated forfeiture clause.

Institute judicial proceedings to enforce the lien

Counted from the date the lien was recorded - the lien continues enforceable for this long by default, absent a written demand from an interested party to sue sooner.

What it counts from. 730 days after notice of construction lien recorded.

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

Nebraska Revised Statute § 52-140 (1)
Official source · statute text retrieved 2026-09-21

“a lien that has become enforceable as provided in sections 52-125 to 52-159 continues enforceable for two years after recording of the lien.”

If the date is missed (the statute's own terms). By its own terms, the lien simply stops being enforceable once this period runs without a judicial proceeding instituted.

Also stated next to this deadline.

Weekend and holiday rollover

NoticeGuard does not model a weekend or holiday extension for Nebraska. The dates above are the plain count from the date you enter. Check whether a Saturday, Sunday or holiday changes your date.

What this rule set does not cover

Keep track of the dates

About the NoticeGuard app

NoticeGuard is an app that turns a job's dates into a countdown for each statutory step, shows the statute text each date was read from, exports a calendar file (.ics) and sends reminders 14, 7 and 1 day before each deadline. It tracks and reminds; it does not file anything for you.

Other states