Georgia mechanics lien deadlines

2 deadlines NoticeGuard models for Georgia: what each one counts from, the statute it was read from, and the statute text.

Information, not legal advice. This app reports what the statute says and cites the section it read. It is not legal advice, it does not file anything for you, and it does not tell you what to do.
Verify with the statute or an attorney. Statutes change, and courts reinterpret them. Every deadline in this app comes from a statute read on the date shown next to its citation - that snapshot can go out of date. Missing a mechanics lien deadline can extinguish your claim permanently, so confirm any deadline you are relying on with an attorney licensed in that state before you act on it.
Data verified: statute text retrieved 2026-09-21 (each citation below carries its own date). Rule data from the NoticeGuard app, source commit 22f9300.

Deadlines at a glance

DeadlineCounted fromApplies toStatute
File claim of lien90 days after last furnishing (last day on site)Original contractor, Subcontractor, Supplier, Preconstruction serviceO.C.G.A. § 44-14-361.1 (a)(2)
Commence a lien action to recover the claim365 days after notice of construction lien recordedOriginal contractor, Subcontractor, Supplier, Preconstruction serviceO.C.G.A. § 44-14-361.1 (a)(3)

Work out a date for Georgia with the calculator

Each deadline, with the statute

File claim of lien

Filed with the clerk of superior court in the county where the property is located, counted from completion of the work or the claimant's own last furnishing of materials.

What it counts from. 90 days after last furnishing (last day on site).

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

O.C.G.A. § 44-14-361.1 (a)(2)
Official source · statute text retrieved 2026-09-21

“The filing for record of his or her claim of lien within 90 days after the completion of the work, the furnishing of the architectural services, or the furnishing or performing of such surveying, engineering services, or interior design services or within 90 days after the material or machinery is furnished in the office of the clerk of the superior court of the county where the property is located. The lien shall include a statement regarding its expiration pursuant to Code Section 44-14-367 and a notice to the owner of the property on which a claim of lien is filed that such owner has the right to contest the lien; the absence of such statement or notice shall invalidate the lien.”

If the date is missed (the statute's own terms). The claim of lien must be filed within this period "to make good" the lien under § 44-14-361.1(a) - Georgia courts (United States Filter Distrib. Group v. Barnett, affirmed by the Georgia Supreme Court) treat this as a strict, non-extendable cutoff, confirmed not extended by the state's general weekend/holiday rollover statute.

Also stated next to this deadline.

Commence a lien action to recover the claim

A lawsuit to recover the amount claimed, counted from the date the claim of lien was filed for record. A separate notice of that lien action must then be filed within 30 days of commencing it - not itself computed here; see this state's limitations.

What it counts from. 365 days after notice of construction lien recorded.

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

O.C.G.A. § 44-14-361.1 (a)(3)
Official source · statute text retrieved 2026-09-21

“The commencement of a lien action for the recovery of the amount of the party's claim within 365 days from the date of filing for record of his or her claim of lien.”

If the date is missed (the statute's own terms). Georgia case law (Action Concrete v. Portrait Homes; Metromont Materials Corp. v. Cargill) treats this deadline as strict - a lienor who misses it cannot revive the lien claim by filing again.

Also stated next to this deadline.

Weekend and holiday rollover

NoticeGuard does not model a weekend or holiday extension for Georgia. The dates above are the plain count from the date you enter. Check whether a Saturday, Sunday or holiday changes your date.