Wyoming mechanics lien deadlines

3 deadlines NoticeGuard models for Wyoming: what each one counts from, the statute it was read from, and the statute text.

Information, not legal advice. This app reports what the statute says and cites the section it read. It is not legal advice, it does not file anything for you, and it does not tell you what to do.
Verify with the statute or an attorney. Statutes change, and courts reinterpret them. Every deadline in this app comes from a statute read on the date shown next to its citation - that snapshot can go out of date. Missing a mechanics lien deadline can extinguish your claim permanently, so confirm any deadline you are relying on with an attorney licensed in that state before you act on it.
Data verified: statute text retrieved 2026-09-21 (each citation below carries its own date). Rule data from the NoticeGuard app, source commit 22f9300.

Deadlines at a glance

DeadlineCounted fromApplies toStatute
File lien statement (contractor)150 days after last furnishing (last day on site), but no later than 150 days after final completion of the original contract (whichever is earlier)Original contractorWyo. Stat. § 29-2-106 (a)
File lien statement (subcontractor, supplier, or preconstruction service provider)120 days after last furnishing (last day on site), but no later than 120 days after final completion of the original contract (whichever is earlier)Subcontractor, Supplier, Preconstruction serviceWyo. Stat. § 29-2-106 (a)
Commence action to foreclose or enforce the lien180 days after notice of construction lien recordedOriginal contractor, Subcontractor, Supplier, Preconstruction serviceWyo. Stat. § 29-2-109 (sole operative sentence)

Work out a date for Wyoming with the calculator

Each deadline, with the statute

File lien statement (contractor)

Filed with the county clerk, counted from this claimant's own last day of work performed or materials furnished - but no later than 150 days after the project's substantial completion, if that comes sooner.

What it counts from. 150 days after last furnishing (last day on site), but no later than 150 days after final completion of the original contract (whichever is earlier).

Applies to. Original contractor.

Wyo. Stat. § 29-2-106 (a)
Official source · statute text retrieved 2026-09-21

“Except as provided in subsection (c) of this section, any contractor asserting a lien under this chapter shall file his lien statement within one hundred fifty (150) days ... of the earlier of: (A) After the last day when work was performed or materials furnished under contract; (B) From the date of substantial completion of the project on which work was performed or materials were furnished under contract.”

If the date is missed (the statute's own terms). The statute's own operative language: the contractor "shall file his lien statement within" this period.

File lien statement (subcontractor, supplier, or preconstruction service provider)

Filed with the county clerk, counted from this claimant's own last day of work performed or materials furnished - but no later than 120 days after the project's substantial completion, if that comes sooner.

What it counts from. 120 days after last furnishing (last day on site), but no later than 120 days after final completion of the original contract (whichever is earlier).

Applies to. Subcontractor, Supplier, Preconstruction service.

Wyo. Stat. § 29-2-106 (a)
Official source · statute text retrieved 2026-09-21

“Except as provided in subsection (c) of this section, any contractor asserting a lien under this chapter shall file his lien statement within one hundred fifty (150) days and every other person asserting a lien under this chapter shall file within one hundred twenty (120) days: (i) Of the earlier of: (A) After the last day when work was performed or materials furnished under contract; (B) From the date of substantial completion of the project on which work was performed or materials were furnished under contract; or (ii) With respect to a subcontractor, after the last day he performed work at the direction of the contractor or other person authorized to provide direction.”

If the date is missed (the statute's own terms). The statute's own operative language: every other claimant "shall file within" this period.

Also stated next to this deadline.

Commence action to foreclose or enforce the lien

Counted from the date the lien statement was filed. The lien stops existing after this period unless an action has been commenced.

What it counts from. 180 days after notice of construction lien recorded.

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

Wyo. Stat. § 29-2-109 (sole operative sentence)
Official source · statute text retrieved 2026-09-21

“All actions to foreclose or enforce a lien under this chapter shall be commenced within one hundred eighty (180) days after the filing of the lien statement. No lien shall continue to exist except by virtue of the provisions of this chapter for more than one hundred eighty (180) days after the lien is filed unless an action to foreclose the lien is instituted.”

If the date is missed (the statute's own terms). The statute's own mechanism: "No lien shall continue to exist... for more than one hundred eighty (180) days after the lien is filed unless an action to foreclose the lien is instituted."

Weekend and holiday rollover

NoticeGuard does not model a weekend or holiday extension for Wyoming. The dates above are the plain count from the date you enter. Check whether a Saturday, Sunday or holiday changes your date.

What this rule set does not cover

Keep track of the dates

About the NoticeGuard app

NoticeGuard is an app that turns a job's dates into a countdown for each statutory step, shows the statute text each date was read from, exports a calendar file (.ics) and sends reminders 14, 7 and 1 day before each deadline. It tracks and reminds; it does not file anything for you.