New Jersey mechanics lien deadlines

4 deadlines NoticeGuard models for New Jersey: what each one counts from, the statute it was read from, and the statute text.

Information, not legal advice. This app reports what the statute says and cites the section it read. It is not legal advice, it does not file anything for you, and it does not tell you what to do.
Verify with the statute or an attorney. Statutes change, and courts reinterpret them. Every deadline in this app comes from a statute read on the date shown next to its citation - that snapshot can go out of date. Missing a mechanics lien deadline can extinguish your claim permanently, so confirm any deadline you are relying on with an attorney licensed in that state before you act on it.
Data verified: statute text retrieved 2026-09-21 (each citation below carries its own date). Rule data from the NoticeGuard app, source commit 22f9300.

Deadlines at a glance

DeadlineCounted fromApplies toStatute
Lodge the lien claim (non-residential)90 days after last furnishing (last day on site)Original contractor, Subcontractor, Supplier, Preconstruction service
only when you do not tick "This is a residential construction contract (a one-, two-, or three-family dwelling)"
N.J.S.A. § 2A:44A-6 a.(2)
Lodge the lien claim (residential construction contract)120 days after last furnishing (last day on site)Original contractor, Subcontractor, Supplier, Preconstruction service
only when you tick "This is a residential construction contract (a one-, two-, or three-family dwelling)"
N.J.S.A. § 2A:44A-6 a.(2)
Notice of Unpaid Balance and Right to File Lien (residential construction contract)60 days after last furnishing (last day on site)Original contractor, Subcontractor, Supplier, Preconstruction service
only when you tick "This is a residential construction contract (a one-, two-, or three-family dwelling)"
N.J.S.A. § 2A:44A-21 (b)(1)
Commence an action to enforce the lien claim365 days after last furnishing (last day on site)Original contractor, Subcontractor, Supplier, Preconstruction serviceN.J.S.A. § 2A:44A-14 (a)

Work out a date for New Jersey with the calculator

Each deadline, with the statute

Lodge the lien claim (non-residential)

Lodged for record with the county clerk, counted from this claimant's own last work, services, material, or equipment provided.

What it counts from. 90 days after last furnishing (last day on site).

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service (when you do not tick "This is a residential construction contract (a one-, two-, or three-family dwelling)").

N.J.S.A. § 2A:44A-6 a.(2)
Official source · statute text retrieved 2026-09-21

“In all cases except those involving a residential construction contract, the lien claim form shall then be lodged for record within 90 days following the date the last work, services, material or equipment was provided for which payment is claimed.”

If the date is missed (the statute's own terms). The lien claim form "shall" be lodged within this period - the statutory lien-claim form itself (§ 8) requires the claimant to swear that it was lodged "within 90 or, if residential construction, 120 days" of last furnishing.

Also stated next to this deadline.

Lodge the lien claim (residential construction contract)

Lodged for record with the county clerk, counted from this claimant's own last work, services, material, or equipment provided - the outer bound; the residential track also requires lodging within 10 days of receiving an arbitrator's determination, a sequential step not computed here (see this rule's notes).

What it counts from. 120 days after last furnishing (last day on site).

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service (when you tick "This is a residential construction contract (a one-, two-, or three-family dwelling)").

N.J.S.A. § 2A:44A-6 a.(2)
Official source · statute text retrieved 2026-09-21

“In the case of a residential construction contract, the lien claim form shall be lodged for record, as required by paragraph (8) of subsection b. of section 21 of P.L.1993, c.318 (C.2A:44A-21), not later than 10 days after receipt by the claimant of the arbitrator's determination, and within 120 days following the date the last work, services, material or equipment was provided for which payment is claimed.”

If the date is missed (the statute's own terms). A residential lien claim not lodged within this outer bound, or within 10 days of the arbitrator's determination if earlier, is invalid - the statute states plainly that missing the arbitrator-determination sub-deadline "shall cause any lien claim to be invalid" (§ 21(b)(8)).

Also stated next to this deadline.

Notice of Unpaid Balance and Right to File Lien (residential construction contract)

Lodged for record, counted from this claimant's own last work, services, material, or equipment provided - a mandatory condition precedent to filing a residential lien claim at all.

What it counts from. 60 days after last furnishing (last day on site).

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service (when you tick "This is a residential construction contract (a one-, two-, or three-family dwelling)").

N.J.S.A. § 2A:44A-21 (b)(1)
Official source · statute text retrieved 2026-09-21

“As a condition precedent to the filing of any lien arising under a residential construction contract, a lien claimant shall first file a Notice of Unpaid Balance and Right to File Lien by lodging for record the Notice within 60 days following the last date that work, services, material or equipment were provided for which payment is claimed...”

If the date is missed (the statute's own terms). The statute states this notice is "a condition precedent to the filing of any lien" on a residential construction contract - without it, no residential lien claim can be filed at all, regardless of the 120-day outer bound.

Also stated next to this deadline.

Commence an action to enforce the lien claim

Counted from this claimant's own last work, services, material, or equipment provided - NOT from the date the lien claim was filed. Can be accelerated to as little as 30 days if a written demand to sue is received; that acceleration is not computed here - read this rule's notes.

What it counts from. 365 days after last furnishing (last day on site).

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

N.J.S.A. § 2A:44A-14 (a)
Official source · statute text retrieved 2026-09-21

“A claimant filing a lien claim shall forfeit all rights to enforce the lien, and shall immediately discharge the lien of record... if the claimant fails to commence an action... to enforce the lien claim: (1) Within one year of the date of the last provision of work, services, material or equipment, payment for which the lien claim was filed; or (2) Within 30 days following receipt of written notice, by personal service or certified mail, return receipt requested, from the owner, community association, contractor, or subcontractor against whose account a lien claim is filed, requiring the claimant to commence an action to enforce the lien claim.”

If the date is missed (the statute's own terms). The statute states the claimant "shall forfeit all rights to enforce the lien" and must immediately discharge it if suit is not timely commenced under either trigger.

Also stated next to this deadline.

Weekend and holiday rollover

NoticeGuard does not model a weekend or holiday extension for New Jersey. The dates above are the plain count from the date you enter. Check whether a Saturday, Sunday or holiday changes your date.