Missouri mechanics lien deadlines

2 deadlines NoticeGuard models for Missouri: what each one counts from, the statute it was read from, and the statute text.

Information, not legal advice. This app reports what the statute says and cites the section it read. It is not legal advice, it does not file anything for you, and it does not tell you what to do.
Verify with the statute or an attorney. Statutes change, and courts reinterpret them. Every deadline in this app comes from a statute read on the date shown next to its citation - that snapshot can go out of date. Missing a mechanics lien deadline can extinguish your claim permanently, so confirm any deadline you are relying on with an attorney licensed in that state before you act on it.
Data verified: statute text retrieved 2026-09-21 (each citation below carries its own date). Rule data from the NoticeGuard app, source commit 22f9300.

Deadlines at a glance

DeadlineCounted fromApplies toStatute
File the mechanic's lien statement180 days after last furnishing (last day on site)Original contractor, Subcontractor, Supplier, Preconstruction serviceRSMo § 429.080 (sole operative sentence)
Commence an action to enforce the lien180 days after notice of construction lien recordedOriginal contractor, Subcontractor, Supplier, Preconstruction serviceRSMo § 429.170 (sole operative sentence)

Work out a date for Missouri with the calculator

Each deadline, with the statute

File the mechanic's lien statement

Filed with the clerk of the circuit court, counted from this claimant's own indebtedness accruing - confirmed by case law to mean this claimant's own last furnishing of labor or material, not overall project completion.

What it counts from. 180 days after last furnishing (last day on site).

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

RSMo § 429.080 (sole operative sentence)
Official source · statute text retrieved 2026-09-21

“It shall be the duty of every original contractor, every journeyman and day laborer... and every other person seeking to obtain the benefit of the provisions of sections 429.010 to 429.340, within six months after the indebtedness shall have accrued... to file with the clerk of the circuit court of the proper county a just and true account of the demand due him or them after all just credits have been given, which is to be a lien upon such building or other improvements...”

If the date is missed (the statute's own terms). The statute states this is a duty owed within the period "to file... a just and true account" that "is to be a lien" - a lien statement not timely filed does not perfect a lien.

Also stated next to this deadline.

Commence an action to enforce the lien

Counted from the date the lien statement was filed. The lien itself expires if suit is not timely commenced.

What it counts from. 180 days after notice of construction lien recorded.

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

RSMo § 429.170 (sole operative sentence)
Official source · statute text retrieved 2026-09-21

“All actions under sections 429.010 to 429.340 shall be commenced within six months after filing the lien, and prosecuted without unnecessary delay to final judgment; and no lien shall continue to exist by virtue of the provisions of said sections, for more than six months after the lien shall be filed, unless within that time an action shall be instituted thereon, as herein prescribed.”

If the date is missed (the statute's own terms). The statute states plainly "no lien shall continue to exist" past this date without a timely-instituted action - a substantive extinguishment, not merely a procedural bar.

Also stated next to this deadline.

Weekend and holiday rollover

NoticeGuard does not model a weekend or holiday extension for Missouri. The dates above are the plain count from the date you enter. Check whether a Saturday, Sunday or holiday changes your date.