8 deadlines NoticeGuard models for Utah: what each one counts from, the statute it was read from, and the statute text.
22f9300.| Deadline | Counted from | Applies to | Statute |
|---|---|---|---|
| Preliminary notice | 20 days after first furnishing (commenced work) | Original contractor, Subcontractor, Supplier | Utah Code § 38-1a-501 (1)(a) |
| Record notice of construction lien (no notice of completion filed) | 180 days after final completion of the original contract | Original contractor, Subcontractor, Supplier only when no date is entered for notice of completion filed and you do not tick "I provided substantial work after the certificate of occupancy or final inspection" | Utah Code § 38-1a-502 (1)(a)(i) |
| Record notice of construction lien (notice of completion filed) | 90 days after notice of completion filed, but no later than 180 days after final completion of the original contract (whichever is earlier) | Original contractor, Subcontractor, Supplier only when a date is entered for notice of completion filed and you do not tick "I provided substantial work after the certificate of occupancy or final inspection" | Utah Code § 38-1a-502 (1)(a)(ii) |
| Record notice of construction lien (substantial work after certificate of occupancy) | 180 days after final completion of your own work | Subcontractor only when you tick "I provided substantial work after the certificate of occupancy or final inspection" | Utah Code § 38-1a-502 (1)(b) |
| Serve copy of recorded lien on owner | 30 days after notice of construction lien recorded | Original contractor, Subcontractor, Supplier | Utah Code § 38-1a-502 (4)(a) |
| File action to enforce the lien | 180 days after notice of construction lien recorded | Original contractor, Subcontractor, Supplier | Utah Code § 38-1a-701 (2)(a)(ii) |
| Notice of preconstruction service | 20 days after preconstruction service commenced | Preconstruction service | Utah Code § 38-1a-401 (1)(a) |
| Record notice of preconstruction lien | 90 days after preconstruction service completed | Preconstruction service | Utah Code § 38-1a-402 (1) |
Filed with the State Construction Registry, counted from the day you commenced providing construction work.
What it counts from. 20 days after first furnishing (commenced work).
Applies to. Original contractor, Subcontractor, Supplier.
Utah Code § 38-1a-501 (1)(a)
Official source · statute text retrieved 2026-09-08
If the date is missed (the statute's own terms). § 38-1a-501(1)(e): "A person who fails to file a preliminary notice as required in this section may not claim a construction lien."
Also stated next to this deadline.
Recorded with each applicable county recorder, counted from final completion of the original contract.
What it counts from. 180 days after final completion of the original contract.
Applies to. Original contractor, Subcontractor, Supplier (when no date is entered for notice of completion filed and you do not tick "I provided substantial work after the certificate of occupancy or final inspection").
Utah Code § 38-1a-502 (1)(a)(i)
Official source · statute text retrieved 2026-09-08
If the date is missed (the statute's own terms). The statute states the notice must be recorded no later than this date in order to claim a construction lien.
Also stated next to this deadline.
Counted from the filing of the notice of completion, and capped by the 180-day outer limit from final completion.
What it counts from. 90 days after notice of completion filed, but no later than 180 days after final completion of the original contract (whichever is earlier).
Applies to. Original contractor, Subcontractor, Supplier (when a date is entered for notice of completion filed and you do not tick "I provided substantial work after the certificate of occupancy or final inspection").
Utah Code § 38-1a-502 (1)(a)(ii)
Official source · statute text retrieved 2026-09-08
If the date is missed (the statute's own terms). The statute states the notice must be recorded no later than this date in order to claim a construction lien.
Also stated next to this deadline.
Counted from final completion of that subcontractor’s own work rather than the original contract.
What it counts from. 180 days after final completion of your own work.
Applies to. Subcontractor (when you tick "I provided substantial work after the certificate of occupancy or final inspection").
Utah Code § 38-1a-502 (1)(b)
Official source · statute text retrieved 2026-09-08
If the date is missed (the statute's own terms). The statute states the notice must be recorded no later than this date in order to claim a construction lien.
Also stated next to this deadline.
Counted from the day the notice of construction lien was filed.
What it counts from. 30 days after notice of construction lien recorded.
Applies to. Original contractor, Subcontractor, Supplier.
Utah Code § 38-1a-502 (4)(a)
Official source · statute text retrieved 2026-09-08
If the date is missed (the statute's own terms). § 38-1a-502(4)(c): failure "precludes the claimant from an award of costs and attorney fees against the reputed owner or record owner in an action to enforce the construction lien." The statute does not state that the lien itself becomes void.
Also stated next to this deadline.
Counted from the day the notice of construction lien was filed.
What it counts from. 180 days after notice of construction lien recorded.
Applies to. Original contractor, Subcontractor, Supplier.
Utah Code § 38-1a-701 (2)(a)(ii)
Official source · statute text retrieved 2026-09-08
If the date is missed (the statute's own terms). § 38-1a-701(4)(a): the lien "is automatically and immediately void if an action to enforce the lien is not filed within the time required by this section."
Also stated next to this deadline.
Filed with the registry, counted from the day preconstruction service commenced.
What it counts from. 20 days after preconstruction service commenced.
Applies to. Preconstruction service.
Utah Code § 38-1a-401 (1)(a)
Official source · statute text retrieved 2026-09-08
If the date is missed (the statute's own terms). § 38-1a-401(1)(b): "A person that fails to file a timely notice of preconstruction service as required in this section may not claim a valid preconstruction lien."
Counted from completion of the preconstruction service you were not paid for.
What it counts from. 90 days after preconstruction service completed.
Applies to. Preconstruction service.
Utah Code § 38-1a-402 (1)
Official source · statute text retrieved 2026-09-08
If the date is missed (the statute's own terms). § 38-1a-402(2): "A claimant who fails to submit a notice of preconstruction lien as provided in Subsection (1) may not claim a preconstruction lien."
NoticeGuard applies this rule to Utah deadlines that land on a Saturday, Sunday or legal holiday. It is the rule as the app stores it, shown with its source.
Utah R. Civ. P. 6 (a)(1)(C)
Official source · retrieved 2026-09-10
NoticeGuard is an app that turns a job's dates into a countdown for each statutory step, shows the statute text each date was read from, exports a calendar file (.ics) and sends reminders 14, 7 and 1 day before each deadline. It tracks and reminds; it does not file anything for you.