Indiana mechanics lien deadlines

3 deadlines NoticeGuard models for Indiana: what each one counts from, the statute it was read from, and the statute text.

Information, not legal advice. This app reports what the statute says and cites the section it read. It is not legal advice, it does not file anything for you, and it does not tell you what to do.
Verify with the statute or an attorney. Statutes change, and courts reinterpret them. Every deadline in this app comes from a statute read on the date shown next to its citation - that snapshot can go out of date. Missing a mechanics lien deadline can extinguish your claim permanently, so confirm any deadline you are relying on with an attorney licensed in that state before you act on it.
Data verified: statute text retrieved 2026-09-21 (each citation below carries its own date). Rule data from the NoticeGuard app, source commit 22f9300.

Deadlines at a glance

DeadlineCounted fromApplies toStatute
File the sworn statement and notice of intention to hold a lien (default)90 days after last furnishing (last day on site)Original contractor, Subcontractor, Supplier, Preconstruction service
only when you do not tick "This is a Class 2 structure (a building or townhouse of one or two dwelling units, or a qualifying outbuilding)"
Indiana Code § 32-28-3-3 (a)
File the sworn statement and notice of intention to hold a lien (Class 2 structure)60 days after last furnishing (last day on site)Original contractor, Subcontractor, Supplier, Preconstruction service
only when you tick "This is a Class 2 structure (a building or townhouse of one or two dwelling units, or a qualifying outbuilding)"
Indiana Code § 32-28-3-3 (b)
File a complaint to enforce the lien365 days after notice of construction lien recordedOriginal contractor, Subcontractor, Supplier, Preconstruction serviceIndiana Code § 32-28-3-6 (a)

Work out a date for Indiana with the calculator

Each deadline, with the statute

File the sworn statement and notice of intention to hold a lien (default)

Filed in duplicate with the county recorder, counted from this claimant's own last labor performed or materials/machinery furnished - the general 90-day period for property that is not a Class 2 structure.

What it counts from. 90 days after last furnishing (last day on site).

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service (when you do not tick "This is a Class 2 structure (a building or townhouse of one or two dwelling units, or a qualifying outbuilding)").

Indiana Code § 32-28-3-3 (a)
Official source · statute text retrieved 2026-09-21

“Except as provided in subsection (b), a person who wishes to acquire a lien upon property, whether the claim is due or not, must file in duplicate a sworn statement and notice of the person's intention to hold a lien upon the property for the amount of the claim: (1) in the recorder's office of the county; and (2) not later than ninety (90) days after performing labor or furnishing materials or machinery described in section 1 of this chapter.”

If the date is missed (the statute's own terms). The statute makes timely filing a condition of the lien itself (a person "who wishes to acquire a lien... must file"); the summary-table cross-reference in § 32-28-3-6 further confirms a missed filing leaves no notice of intention to anchor a later foreclosure action.

Also stated next to this deadline.

File the sworn statement and notice of intention to hold a lien (Class 2 structure)

Filed in duplicate with the county recorder, counted from this claimant's own last labor performed or materials/machinery furnished - the shorter 60-day period for a Class 2 structure (a building or townhouse of one or two dwelling units, or a qualifying outbuilding), regardless of whether anyone occupies it.

What it counts from. 60 days after last furnishing (last day on site).

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service (when you tick "This is a Class 2 structure (a building or townhouse of one or two dwelling units, or a qualifying outbuilding)").

Indiana Code § 32-28-3-3 (b)
Official source · statute text retrieved 2026-09-21

“This subsection applies to a person that performs labor or furnishes materials or machinery described in section 1 of this chapter related to a Class 2 structure (as defined in IC 22-12-1-5) or an improvement on the same real estate auxiliary to a Class 2 structure (as defined in IC 22-12-1-5). A person who wishes to acquire a lien upon property, whether the claim is due or not, must file in duplicate a sworn statement and notice of the person's intention to hold a lien upon the property for the amount of the claim: (1) in the recorder's office of the county; and (2) not later than sixty (60) days after performing labor or furnishing materials or machinery described in section 1 of this chapter.”

If the date is missed (the statute's own terms). The statute makes timely filing a condition of the lien itself (a person "who wishes to acquire a lien... must file"); the summary-table cross-reference in § 32-28-3-6 further confirms a missed filing leaves no notice of intention to anchor a later foreclosure action.

Also stated next to this deadline.

File a complaint to enforce the lien

Filed in the circuit or superior court of the county where the property is located, counted from the date the sworn statement and notice of intention to hold a lien was recorded.

What it counts from. 365 days after notice of construction lien recorded.

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

Indiana Code § 32-28-3-6 (a)
Official source · statute text retrieved 2026-09-21

“A person may enforce a lien by filing a complaint in the circuit or superior court of the county where the real estate or property that is the subject of the lien is situated. The complaint must be filed not later than one (1) year after: (1) the date the statement and notice of intention to hold a lien was recorded under section 3 of this chapter; or (2) subject to subsection (c), the expiration of the credit, if a credit is given.”

If the date is missed (the statute's own terms). The statute states plainly: "if a lien is not enforced within the time set forth in subsection (a), the lien is void" (§ 32-28-3-6(b)) - a right-extinguishing deadline, not merely procedural.

Also stated next to this deadline.

Weekend and holiday rollover

NoticeGuard does not model a weekend or holiday extension for Indiana. The dates above are the plain count from the date you enter. Check whether a Saturday, Sunday or holiday changes your date.

What this rule set does not cover