Michigan mechanics lien deadlines

4 deadlines NoticeGuard models for Michigan: what each one counts from, the statute it was read from, and the statute text.

Information, not legal advice. This app reports what the statute says and cites the section it read. It is not legal advice, it does not file anything for you, and it does not tell you what to do.
Verify with the statute or an attorney. Statutes change, and courts reinterpret them. Every deadline in this app comes from a statute read on the date shown next to its citation - that snapshot can go out of date. Missing a mechanics lien deadline can extinguish your claim permanently, so confirm any deadline you are relying on with an attorney licensed in that state before you act on it.
Data verified: statute text retrieved 2026-09-21 (each citation below carries its own date). Rule data from the NoticeGuard app, source commit 22f9300.

Deadlines at a glance

DeadlineCounted fromApplies toStatute
Notice of furnishing20 days after first furnishing (commenced work)Subcontractor, Supplier, Preconstruction serviceMCL § 570.1109 (1)
Record the claim of lien90 days after last furnishing (last day on site)Original contractor, Subcontractor, Supplier, Preconstruction serviceMCL § 570.1111 (1)
Serve a copy of the recorded claim of lien15 days after notice of construction lien recordedOriginal contractor, Subcontractor, Supplier, Preconstruction serviceMCL § 570.1111 (5)
Commence an action to enforce the construction lien365 days after notice of construction lien recordedOriginal contractor, Subcontractor, Supplier, Preconstruction serviceMCL § 570.1117 (1)

Work out a date for Michigan with the calculator

Each deadline, with the statute

Notice of furnishing

Served on the designee (and the general contractor, if any) named in the notice of commencement, counted from the day this claimant first furnished labor or material.

What it counts from. 20 days after first furnishing (commenced work).

Applies to. Subcontractor, Supplier, Preconstruction service.

MCL § 570.1109 (1)
Official source · statute text retrieved 2026-09-21

“Except as otherwise provided in sections 108 and 108a, a subcontractor or supplier that contracts to provide an improvement to real property shall provide a notice of furnishing to the designee and the general contractor, if any, as named in the notice of commencement at the address shown in the notice of commencement, either personally or by certified mail, within 20 days after furnishing the first labor or material... A contractor is not required to provide a notice of furnishing to preserve lien rights arising from his or her contract directly with an owner or lessee.”

If the date is missed (the statute's own terms). A late or missing notice does not automatically void the lien, but forfeits lien rights for work furnished before the (late) notice to the extent the owner already paid the contractor in reliance on a sworn statement or waiver (§ 109(6)) - see this rule's notes and `limitations` for why this makes the deadline more consequential than it first appears.

Also stated next to this deadline.

Record the claim of lien

Recorded with the register of deeds, counted from this claimant's own last furnishing of labor or material under their own contract.

What it counts from. 90 days after last furnishing (last day on site).

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

MCL § 570.1111 (1)
Official source · statute text retrieved 2026-09-21

“Notwithstanding section 109, the right of a contractor, subcontractor, laborer, or supplier to a construction lien created by this act shall cease to exist unless, within 90 days after the lien claimant's last furnishing of labor or material for the improvement, pursuant to the lien claimant's contract, a claim of lien is recorded in the office of the register of deeds for each county where the real property to which the improvement was made is located.”

If the date is missed (the statute's own terms). The statute states plainly: the right to a construction lien "shall cease to exist" if the claim of lien is not recorded within this period - a right-extinguishing deadline, not merely a procedural bar.

Also stated next to this deadline.

Serve a copy of the recorded claim of lien

Served on the designee (personally or by certified mail), counted from the date the claim of lien was recorded.

What it counts from. 15 days after notice of construction lien recorded.

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

MCL § 570.1111 (5)
Official source · statute text retrieved 2026-09-21

“Each contractor, subcontractor, supplier, laborer, or agent of a group of laborers authorized under subsection (6) recording a claim of lien, within 15 days after the date of the recording, shall serve on the designee personally or by certified mail, return receipt requested, at the address shown on the notice of commencement, a copy of the claim of lien and a copy of any proof of service recorded in connection with the claim of lien.”

If the date is missed (the statute's own terms). The statute uses "shall serve" as a mandatory instruction - a real, separate statutory step following recording, distinct from the 90-day recording deadline itself.

Also stated next to this deadline.

Commence an action to enforce the construction lien

Counted from the date the claim of lien was recorded. A notice of lis pendens must be recorded at the same time suit is commenced.

What it counts from. 365 days after notice of construction lien recorded.

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

MCL § 570.1117 (1)
Official source · statute text retrieved 2026-09-21

“Proceedings for the enforcement of a construction lien and the foreclosure of any interests subject to the construction lien shall not be brought later than 1 year after the date the claim of lien was recorded.”

If the date is missed (the statute's own terms). The statute states proceedings "shall not be brought later than" this date - a hard outer bound on enforcement.

Also stated next to this deadline.

Weekend and holiday rollover

NoticeGuard does not model a weekend or holiday extension for Michigan. The dates above are the plain count from the date you enter. Check whether a Saturday, Sunday or holiday changes your date.