12 deadlines NoticeGuard models for Texas: what each one counts from, the statute it was read from, and the statute text.
22f9300.| Deadline | Counted from | Applies to | Statute |
|---|---|---|---|
| Original contractor's lien affidavit (commercial) | The 15th day of the 4th month after final completion of the original contract | Original contractor only when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)" | Texas Property Code § 53.052 (a)(1) |
| Original contractor's lien affidavit (residential) | The 15th day of the 3rd month after final completion of the original contract | Original contractor only when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)" | Texas Property Code § 53.052 (a)(2) |
| Subcontractor's or supplier's lien affidavit (commercial) | The 15th day of the 4th month after last furnishing (last day on site) | Subcontractor, Supplier, Preconstruction service only when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)" | Texas Property Code § 53.052 (b) |
| Subcontractor's or supplier's lien affidavit (residential) | The 15th day of the 3rd month after last furnishing (last day on site) | Subcontractor, Supplier, Preconstruction service only when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)" | Texas Property Code § 53.052 (c) |
| Retainage claim's lien affidavit | The 15th day of the 3rd month after final completion of the original contract | Subcontractor, Supplier, Preconstruction service only when you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)" | Texas Property Code § 53.052 (d) |
| Notice of claim for unpaid labor or materials (commercial) | The 15th day of the 3rd month after last furnishing (last day on site) | Subcontractor, Supplier, Preconstruction service only when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)" | Texas Property Code § 53.056 (a-1)(1) |
| Notice of claim for unpaid labor or materials (residential) | The 15th day of the 2nd month after last furnishing (last day on site) | Subcontractor, Supplier, Preconstruction service only when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)" | Texas Property Code § 53.056 (a-1)(2) |
| Notice of claim for unpaid retainage | 30 days after final completion of the original contract | Subcontractor, Supplier, Preconstruction service only when you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)" | Texas Property Code § 53.057 (a-1) |
| Suit to foreclose the lien (original contractor, commercial) | The 15th day of the 16th month after final completion of the original contract | Original contractor only when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)" | Texas Property Code § 53.158 (a) |
| Suit to foreclose the lien (original contractor, residential) | The 15th day of the 15th month after final completion of the original contract | Original contractor only when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)" | Texas Property Code § 53.158 (a) |
| Suit to foreclose the lien (subcontractor or supplier, commercial) | The 15th day of the 16th month after last furnishing (last day on site) | Subcontractor, Supplier, Preconstruction service only when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)" | Texas Property Code § 53.158 (a) |
| Suit to foreclose the lien (subcontractor or supplier, residential) | The 15th day of the 15th month after last furnishing (last day on site) | Subcontractor, Supplier, Preconstruction service only when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)" | Texas Property Code § 53.158 (a) |
Filed with the county clerk, due the 15th day of the 4th month after the month the original contractor's work was completed, terminated, or abandoned.
What it counts from. The 15th day of the 4th month after final completion of the original contract.
Applies to. Original contractor (when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").
Texas Property Code § 53.052 (a)(1)
Official source · statute text retrieved 2026-09-21
If the date is missed (the statute's own terms). The affidavit must be filed by this date to perfect the lien under Chapter 53 - this is the "NECESSARY PROCEDURES" § 53.051 requires to be followed.
Also stated next to this deadline.
Filed with the county clerk, due the 15th day of the 3rd month after the month the original contractor's work was completed, terminated, or abandoned - one month earlier than the commercial track.
What it counts from. The 15th day of the 3rd month after final completion of the original contract.
Applies to. Original contractor (when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").
Texas Property Code § 53.052 (a)(2)
Official source · statute text retrieved 2026-09-21
If the date is missed (the statute's own terms). The affidavit must be filed by this date to perfect the lien under Chapter 53.
Also stated next to this deadline.
Filed with the county clerk, due the 15th day of the 4th month after the month this claimant last provided labor or materials.
What it counts from. The 15th day of the 4th month after last furnishing (last day on site).
Applies to. Subcontractor, Supplier, Preconstruction service (when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").
Texas Property Code § 53.052 (b)
Official source · statute text retrieved 2026-09-21
If the date is missed (the statute's own terms). The affidavit must be filed by this date to perfect the lien under Chapter 53.
Also stated next to this deadline.
Filed with the county clerk, due the 15th day of the 3rd month after the month this claimant last provided labor or materials - one month earlier than the commercial track.
What it counts from. The 15th day of the 3rd month after last furnishing (last day on site).
Applies to. Subcontractor, Supplier, Preconstruction service (when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").
Texas Property Code § 53.052 (c)
Official source · statute text retrieved 2026-09-21
If the date is missed (the statute's own terms). The affidavit must be filed by this date to perfect the lien under Chapter 53.
Also stated next to this deadline.
Filed with the county clerk, due the 15th day of the 3rd month after the month the ORIGINAL CONTRACT (not this claimant's own work) was completed, terminated, or abandoned - the same 3-month period regardless of project type.
What it counts from. The 15th day of the 3rd month after final completion of the original contract.
Applies to. Subcontractor, Supplier, Preconstruction service (when you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").
Texas Property Code § 53.052 (d)
Official source · statute text retrieved 2026-09-21
If the date is missed (the statute's own terms). The affidavit must be filed by this date to perfect a lien for the unpaid retainage specifically.
Also stated next to this deadline.
Sent to the owner and the original contractor, due the 15th day of the 3rd month after the month labor or materials were provided. Shown for this claimant's LAST month of work - the statute actually requires one notice per month worked, not a single deadline; see this rule's notes.
What it counts from. The 15th day of the 3rd month after last furnishing (last day on site).
Applies to. Subcontractor, Supplier, Preconstruction service (when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").
Texas Property Code § 53.056 (a-1)(1)
Official source · statute text retrieved 2026-09-21
If the date is missed (the statute's own terms). § 53.056(a): "a claimant other than an original contractor must give the notice ... for the lien to be valid" - this is a genuine precondition to lien validity, not merely a payment-priority step.
Also stated next to this deadline.
Sent to the owner and the original contractor, due the 15th day of the 2nd month after the month labor or materials were provided - one month earlier than the commercial track. Shown for this claimant's LAST month of work; see this rule's notes.
What it counts from. The 15th day of the 2nd month after last furnishing (last day on site).
Applies to. Subcontractor, Supplier, Preconstruction service (when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").
Texas Property Code § 53.056 (a-1)(2)
Official source · statute text retrieved 2026-09-21
If the date is missed (the statute's own terms). § 53.056(a): this notice is required "for the lien to be valid" - a genuine precondition, not merely a payment-priority step.
Also stated next to this deadline.
Sent to the owner and the original contractor, due 30 days after this claimant's own contract (or, if earlier, the original contract) is completed, terminated, or abandoned.
What it counts from. 30 days after final completion of the original contract.
Applies to. Subcontractor, Supplier, Preconstruction service (when you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").
Texas Property Code § 53.057 (a-1)
Official source · statute text retrieved 2026-09-21
If the date is missed (the statute's own terms). § 53.057(a): required "for a lien for unpaid retainage to be valid" - a genuine precondition to that specific claim, not merely a payment-priority step.
Also stated next to this deadline.
Must be brought within the first anniversary of the original contractor's own lien-affidavit deadline - computed here as the 15th day of the 16th month after the month the original contractor's work was completed, terminated, or abandoned (4 months + 12).
What it counts from. The 15th day of the 16th month after final completion of the original contract.
Applies to. Original contractor (when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").
Texas Property Code § 53.158 (a)
Official source · statute text retrieved 2026-09-21
If the date is missed (the statute's own terms). The statute states plainly: past this date, without a timely-filed suit, "the lien claimant's rights to pursue a suit to foreclose a lien are not revived" (§ 53.158(a-1)).
Also stated next to this deadline.
Must be brought within the first anniversary of the original contractor's own lien-affidavit deadline - computed here as the 15th day of the 15th month after the month the original contractor's work was completed, terminated, or abandoned (3 months + 12).
What it counts from. The 15th day of the 15th month after final completion of the original contract.
Applies to. Original contractor (when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").
Texas Property Code § 53.158 (a)
Official source · statute text retrieved 2026-09-21
If the date is missed (the statute's own terms). Past this date, without a timely-filed suit, the lien claimant's foreclosure rights are not revived (§ 53.158(a-1)).
Also stated next to this deadline.
Must be brought within the first anniversary of this claimant's own lien-affidavit deadline - computed here as the 15th day of the 16th month after the month this claimant last provided labor or materials (4 months + 12).
What it counts from. The 15th day of the 16th month after last furnishing (last day on site).
Applies to. Subcontractor, Supplier, Preconstruction service (when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").
Texas Property Code § 53.158 (a)
Official source · statute text retrieved 2026-09-21
If the date is missed (the statute's own terms). Past this date, without a timely-filed suit, the lien claimant's foreclosure rights are not revived (§ 53.158(a-1)).
Also stated next to this deadline.
Must be brought within the first anniversary of this claimant's own lien-affidavit deadline - computed here as the 15th day of the 15th month after the month this claimant last provided labor or materials (3 months + 12).
What it counts from. The 15th day of the 15th month after last furnishing (last day on site).
Applies to. Subcontractor, Supplier, Preconstruction service (when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").
Texas Property Code § 53.158 (a)
Official source · statute text retrieved 2026-09-21
If the date is missed (the statute's own terms). Past this date, without a timely-filed suit, the lien claimant's foreclosure rights are not revived (§ 53.158(a-1)).
Also stated next to this deadline.
NoticeGuard does not model a weekend or holiday extension for Texas. The dates above are the plain count from the date you enter. Check whether a Saturday, Sunday or holiday changes your date.