Texas mechanics lien deadlines

12 deadlines NoticeGuard models for Texas: what each one counts from, the statute it was read from, and the statute text.

Information, not legal advice. This app reports what the statute says and cites the section it read. It is not legal advice, it does not file anything for you, and it does not tell you what to do.
Verify with the statute or an attorney. Statutes change, and courts reinterpret them. Every deadline in this app comes from a statute read on the date shown next to its citation - that snapshot can go out of date. Missing a mechanics lien deadline can extinguish your claim permanently, so confirm any deadline you are relying on with an attorney licensed in that state before you act on it.
Data verified: statute text retrieved 2026-09-21 (each citation below carries its own date). Rule data from the NoticeGuard app, source commit 22f9300.

Deadlines at a glance

DeadlineCounted fromApplies toStatute
Original contractor's lien affidavit (commercial)The 15th day of the 4th month after final completion of the original contractOriginal contractor
only when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)"
Texas Property Code § 53.052 (a)(1)
Original contractor's lien affidavit (residential)The 15th day of the 3rd month after final completion of the original contractOriginal contractor
only when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)"
Texas Property Code § 53.052 (a)(2)
Subcontractor's or supplier's lien affidavit (commercial)The 15th day of the 4th month after last furnishing (last day on site)Subcontractor, Supplier, Preconstruction service
only when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)"
Texas Property Code § 53.052 (b)
Subcontractor's or supplier's lien affidavit (residential)The 15th day of the 3rd month after last furnishing (last day on site)Subcontractor, Supplier, Preconstruction service
only when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)"
Texas Property Code § 53.052 (c)
Retainage claim's lien affidavitThe 15th day of the 3rd month after final completion of the original contractSubcontractor, Supplier, Preconstruction service
only when you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)"
Texas Property Code § 53.052 (d)
Notice of claim for unpaid labor or materials (commercial)The 15th day of the 3rd month after last furnishing (last day on site)Subcontractor, Supplier, Preconstruction service
only when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)"
Texas Property Code § 53.056 (a-1)(1)
Notice of claim for unpaid labor or materials (residential)The 15th day of the 2nd month after last furnishing (last day on site)Subcontractor, Supplier, Preconstruction service
only when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)"
Texas Property Code § 53.056 (a-1)(2)
Notice of claim for unpaid retainage30 days after final completion of the original contractSubcontractor, Supplier, Preconstruction service
only when you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)"
Texas Property Code § 53.057 (a-1)
Suit to foreclose the lien (original contractor, commercial)The 15th day of the 16th month after final completion of the original contractOriginal contractor
only when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)"
Texas Property Code § 53.158 (a)
Suit to foreclose the lien (original contractor, residential)The 15th day of the 15th month after final completion of the original contractOriginal contractor
only when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)"
Texas Property Code § 53.158 (a)
Suit to foreclose the lien (subcontractor or supplier, commercial)The 15th day of the 16th month after last furnishing (last day on site)Subcontractor, Supplier, Preconstruction service
only when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)"
Texas Property Code § 53.158 (a)
Suit to foreclose the lien (subcontractor or supplier, residential)The 15th day of the 15th month after last furnishing (last day on site)Subcontractor, Supplier, Preconstruction service
only when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)"
Texas Property Code § 53.158 (a)

Work out a date for Texas with the calculator

Each deadline, with the statute

Original contractor's lien affidavit (commercial)

Filed with the county clerk, due the 15th day of the 4th month after the month the original contractor's work was completed, terminated, or abandoned.

What it counts from. The 15th day of the 4th month after final completion of the original contract.

Applies to. Original contractor (when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").

Texas Property Code § 53.052 (a)(1)
Official source · statute text retrieved 2026-09-21

“An original contractor claiming the lien must file an affidavit with the county clerk: (1) for projects other than residential construction projects, not later than the 15th day of the fourth month after the month in which the original contractor's work was completed, terminated, or abandoned...”

If the date is missed (the statute's own terms). The affidavit must be filed by this date to perfect the lien under Chapter 53 - this is the "NECESSARY PROCEDURES" § 53.051 requires to be followed.

Also stated next to this deadline.

Original contractor's lien affidavit (residential)

Filed with the county clerk, due the 15th day of the 3rd month after the month the original contractor's work was completed, terminated, or abandoned - one month earlier than the commercial track.

What it counts from. The 15th day of the 3rd month after final completion of the original contract.

Applies to. Original contractor (when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").

Texas Property Code § 53.052 (a)(2)
Official source · statute text retrieved 2026-09-21

“for residential construction projects, not later than the 15th day of the third month after the month in which the original contractor's work was completed, terminated, or abandoned.”

If the date is missed (the statute's own terms). The affidavit must be filed by this date to perfect the lien under Chapter 53.

Also stated next to this deadline.

Subcontractor's or supplier's lien affidavit (commercial)

Filed with the county clerk, due the 15th day of the 4th month after the month this claimant last provided labor or materials.

What it counts from. The 15th day of the 4th month after last furnishing (last day on site).

Applies to. Subcontractor, Supplier, Preconstruction service (when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").

Texas Property Code § 53.052 (b)
Official source · statute text retrieved 2026-09-21

“Except as provided by Subsection (c) or (d), a claimant other than an original contractor claiming the lien must file an affidavit with the county clerk not later than the 15th day of the fourth month after the later of: (1) the month the claimant last provided labor or materials; or (2) the month the claimant would normally have been required to deliver the last of specially fabricated materials that have not been actually delivered.”

If the date is missed (the statute's own terms). The affidavit must be filed by this date to perfect the lien under Chapter 53.

Also stated next to this deadline.

Subcontractor's or supplier's lien affidavit (residential)

Filed with the county clerk, due the 15th day of the 3rd month after the month this claimant last provided labor or materials - one month earlier than the commercial track.

What it counts from. The 15th day of the 3rd month after last furnishing (last day on site).

Applies to. Subcontractor, Supplier, Preconstruction service (when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").

Texas Property Code § 53.052 (c)
Official source · statute text retrieved 2026-09-21

“A claimant other than an original contractor claiming a lien arising from a residential construction project must file an affidavit with the county clerk not later than the 15th day of the third month after the later of: (1) the month the claimant last provided labor or materials; or (2) the month the claimant would normally have been required to deliver the last of specially fabricated materials that have not been actually delivered.”

If the date is missed (the statute's own terms). The affidavit must be filed by this date to perfect the lien under Chapter 53.

Also stated next to this deadline.

Retainage claim's lien affidavit

Filed with the county clerk, due the 15th day of the 3rd month after the month the ORIGINAL CONTRACT (not this claimant's own work) was completed, terminated, or abandoned - the same 3-month period regardless of project type.

What it counts from. The 15th day of the 3rd month after final completion of the original contract.

Applies to. Subcontractor, Supplier, Preconstruction service (when you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").

Texas Property Code § 53.052 (d)
Official source · statute text retrieved 2026-09-21

“A claimant other than an original contractor claiming a lien for retainage must file an affidavit with the county clerk not later than the 15th day of the third month after the month in which the original contract under which the claimant performed was completed, terminated, or abandoned.”

If the date is missed (the statute's own terms). The affidavit must be filed by this date to perfect a lien for the unpaid retainage specifically.

Also stated next to this deadline.

Notice of claim for unpaid labor or materials (commercial)

Sent to the owner and the original contractor, due the 15th day of the 3rd month after the month labor or materials were provided. Shown for this claimant's LAST month of work - the statute actually requires one notice per month worked, not a single deadline; see this rule's notes.

What it counts from. The 15th day of the 3rd month after last furnishing (last day on site).

Applies to. Subcontractor, Supplier, Preconstruction service (when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").

Texas Property Code § 53.056 (a-1)(1)
Official source · statute text retrieved 2026-09-21

“For all unpaid labor or materials provided, the claimant must send a notice of claim for unpaid labor or materials to the owner or reputed owner and the original contractor. The notice must be sent: (1) for projects other than residential construction projects, not later than the 15th day of the third month after the month during which: (A) the labor or materials were provided; or (B) the undelivered specially fabricated materials would normally have been delivered...”

If the date is missed (the statute's own terms). § 53.056(a): "a claimant other than an original contractor must give the notice ... for the lien to be valid" - this is a genuine precondition to lien validity, not merely a payment-priority step.

Also stated next to this deadline.

Notice of claim for unpaid labor or materials (residential)

Sent to the owner and the original contractor, due the 15th day of the 2nd month after the month labor or materials were provided - one month earlier than the commercial track. Shown for this claimant's LAST month of work; see this rule's notes.

What it counts from. The 15th day of the 2nd month after last furnishing (last day on site).

Applies to. Subcontractor, Supplier, Preconstruction service (when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").

Texas Property Code § 53.056 (a-1)(2)
Official source · statute text retrieved 2026-09-21

“for residential construction projects, not later than the 15th day of the second month after the month during which: (A) the labor or materials were provided; or (B) the undelivered specially fabricated materials would normally have been delivered.”

If the date is missed (the statute's own terms). § 53.056(a): this notice is required "for the lien to be valid" - a genuine precondition, not merely a payment-priority step.

Also stated next to this deadline.

Notice of claim for unpaid retainage

Sent to the owner and the original contractor, due 30 days after this claimant's own contract (or, if earlier, the original contract) is completed, terminated, or abandoned.

What it counts from. 30 days after final completion of the original contract.

Applies to. Subcontractor, Supplier, Preconstruction service (when you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").

Texas Property Code § 53.057 (a-1)
Official source · statute text retrieved 2026-09-21

“The claimant must send the notice of claim for unpaid retainage to the owner or reputed owner and the original contractor not later than the earlier of: (1) the 30th day after the date the claimant's contract is completed, terminated, or abandoned; or (2) the 30th day after the date the original contract is terminated or abandoned.”

If the date is missed (the statute's own terms). § 53.057(a): required "for a lien for unpaid retainage to be valid" - a genuine precondition to that specific claim, not merely a payment-priority step.

Also stated next to this deadline.

Suit to foreclose the lien (original contractor, commercial)

Must be brought within the first anniversary of the original contractor's own lien-affidavit deadline - computed here as the 15th day of the 16th month after the month the original contractor's work was completed, terminated, or abandoned (4 months + 12).

What it counts from. The 15th day of the 16th month after final completion of the original contract.

Applies to. Original contractor (when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").

Texas Property Code § 53.158 (a)
Official source · statute text retrieved 2026-09-21

“Except as provided by Subsection (a-2), suit must be brought to foreclose the lien not later than the first anniversary of the last day a claimant may file the lien affidavit under Section 53.052.”

If the date is missed (the statute's own terms). The statute states plainly: past this date, without a timely-filed suit, "the lien claimant's rights to pursue a suit to foreclose a lien are not revived" (§ 53.158(a-1)).

Also stated next to this deadline.

Suit to foreclose the lien (original contractor, residential)

Must be brought within the first anniversary of the original contractor's own lien-affidavit deadline - computed here as the 15th day of the 15th month after the month the original contractor's work was completed, terminated, or abandoned (3 months + 12).

What it counts from. The 15th day of the 15th month after final completion of the original contract.

Applies to. Original contractor (when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").

Texas Property Code § 53.158 (a)
Official source · statute text retrieved 2026-09-21

“Except as provided by Subsection (a-2), suit must be brought to foreclose the lien not later than the first anniversary of the last day a claimant may file the lien affidavit under Section 53.052.”

If the date is missed (the statute's own terms). Past this date, without a timely-filed suit, the lien claimant's foreclosure rights are not revived (§ 53.158(a-1)).

Also stated next to this deadline.

Suit to foreclose the lien (subcontractor or supplier, commercial)

Must be brought within the first anniversary of this claimant's own lien-affidavit deadline - computed here as the 15th day of the 16th month after the month this claimant last provided labor or materials (4 months + 12).

What it counts from. The 15th day of the 16th month after last furnishing (last day on site).

Applies to. Subcontractor, Supplier, Preconstruction service (when you do not tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").

Texas Property Code § 53.158 (a)
Official source · statute text retrieved 2026-09-21

“Except as provided by Subsection (a-2), suit must be brought to foreclose the lien not later than the first anniversary of the last day a claimant may file the lien affidavit under Section 53.052.”

If the date is missed (the statute's own terms). Past this date, without a timely-filed suit, the lien claimant's foreclosure rights are not revived (§ 53.158(a-1)).

Also stated next to this deadline.

Suit to foreclose the lien (subcontractor or supplier, residential)

Must be brought within the first anniversary of this claimant's own lien-affidavit deadline - computed here as the 15th day of the 15th month after the month this claimant last provided labor or materials (3 months + 12).

What it counts from. The 15th day of the 15th month after last furnishing (last day on site).

Applies to. Subcontractor, Supplier, Preconstruction service (when you tick "This is a residential construction project" and you do not tick "The original contract was signed before January 1, 2022 (an earlier Texas statute governs it, and this app does not cover that one)").

Texas Property Code § 53.158 (a)
Official source · statute text retrieved 2026-09-21

“Except as provided by Subsection (a-2), suit must be brought to foreclose the lien not later than the first anniversary of the last day a claimant may file the lien affidavit under Section 53.052.”

If the date is missed (the statute's own terms). Past this date, without a timely-filed suit, the lien claimant's foreclosure rights are not revived (§ 53.158(a-1)).

Also stated next to this deadline.

Weekend and holiday rollover

NoticeGuard does not model a weekend or holiday extension for Texas. The dates above are the plain count from the date you enter. Check whether a Saturday, Sunday or holiday changes your date.

What this rule set does not cover

Keep track of the dates

About the NoticeGuard app

NoticeGuard is an app that turns a job's dates into a countdown for each statutory step, shows the statute text each date was read from, exports a calendar file (.ics) and sends reminders 14, 7 and 1 day before each deadline. It tracks and reminds; it does not file anything for you.

Other states