Virginia mechanics lien deadlines

3 deadlines NoticeGuard models for Virginia: what each one counts from, the statute it was read from, and the statute text.

Information, not legal advice. This app reports what the statute says and cites the section it read. It is not legal advice, it does not file anything for you, and it does not tell you what to do.
Verify with the statute or an attorney. Statutes change, and courts reinterpret them. Every deadline in this app comes from a statute read on the date shown next to its citation - that snapshot can go out of date. Missing a mechanics lien deadline can extinguish your claim permanently, so confirm any deadline you are relying on with an attorney licensed in that state before you act on it.
Data verified: statute text retrieved 2026-09-21 (each citation below carries its own date). Rule data from the NoticeGuard app, source commit 22f9300.

Deadlines at a glance

DeadlineCounted fromApplies toStatute
File the memorandum of lien90 days after last furnishing (last day on site), but no later than 90 days after final completion of the original contract (whichever is earlier)Original contractor, Subcontractor, Supplier, Preconstruction serviceCode of Virginia § 43-4 (sole operative paragraph)
Commence suit to enforce the lien180 days after notice of construction lien recordedOriginal contractor, Subcontractor, Supplier, Preconstruction serviceCode of Virginia § 43-17 (sole operative paragraph)
Second notice for personal liability of owner or general contractor30 days after final completion of the original contractSubcontractor, Supplier, Preconstruction serviceCode of Virginia § 43-11 (2)

Work out a date for Virginia with the calculator

Each deadline, with the statute

File the memorandum of lien

Filed with the clerk's office, counted from this claimant's own last labor or materials furnished - capped at 90 days after completion of the building or structure (or the work otherwise terminated), if that is tighter.

What it counts from. 90 days after last furnishing (last day on site), but no later than 90 days after final completion of the original contract (whichever is earlier).

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

Code of Virginia § 43-4 (sole operative paragraph)
Official source · statute text retrieved 2026-09-21

“A general contractor, or any other lien claimant under §§ 43-7 and 43-9, in order to perfect the lien given by § 43-3, provided such lien has not been barred by § 43-4.01 C, shall file a memorandum of lien at any time after the work is commenced or material furnished, but not later than 90 days from the last day of the month in which he last performs labor or furnishes material, and in no event later than 90 days from the time such building, structure, or railroad is completed, or the work thereon otherwise terminated.”

If the date is missed (the statute's own terms). The memorandum "shall" be filed within this period "in order to perfect the lien" - a lien not timely filed is not perfected.

Also stated next to this deadline.

Commence suit to enforce the lien

Counted from the date the memorandum of lien was recorded. The statute actually sets this as the LATER of that count or 60 days after completion - this app shows only the recording-based count; see this rule's notes.

What it counts from. 180 days after notice of construction lien recorded.

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

Code of Virginia § 43-17 (sole operative paragraph)
Official source · statute text retrieved 2026-09-21

“No suit to enforce any lien perfected under §§ 43-4, 43-5 and 43-7 to 43-10 shall be brought after six months from the time when the memorandum of lien was recorded or after sixty days from the time the building, structure or railroad was completed or the work thereon otherwise terminated, whichever time shall last occur...”

If the date is missed (the statute's own terms). A suit brought after this period is barred - the statute states it "shall [not] be brought after" either date, whichever is later.

Also stated next to this deadline.

Second notice for personal liability of owner or general contractor

An optional, separate cause of action (not the lien itself) - a verified statement of the claimant's actual claim, sent to the owner and general contractor, due within 30 days after the building is completed or the work otherwise terminated.

What it counts from. 30 days after final completion of the original contract.

Applies to. Subcontractor, Supplier, Preconstruction service.

Code of Virginia § 43-11 (2)
Official source · statute text retrieved 2026-09-21

“Additionally, if such subcontractor, or person furnishing labor or material shall at any time after the work is done or material furnished by him and before the expiration of thirty days from the time such building or structure is completed or the work thereon otherwise terminated furnish the owner thereof or his agent and also the general contractor... with a second notice stating a correct account, verified by affidavit, of his actual claim against the general contractor or subcontractor, for work done or materials furnished and of the amount due, then the owner, or the general contractor, if he alone was notified, shall be personally liable to the claimant...”

If the date is missed (the statute's own terms). Sending this notice within the period is what makes the owner (or general contractor) personally liable for the amount due - a genuinely separate, optional remedy from perfecting the lien itself under § 43-4.

Also stated next to this deadline.

Weekend and holiday rollover

NoticeGuard does not model a weekend or holiday extension for Virginia. The dates above are the plain count from the date you enter. Check whether a Saturday, Sunday or holiday changes your date.

What this rule set does not cover

Keep track of the dates

About the NoticeGuard app

NoticeGuard is an app that turns a job's dates into a countdown for each statutory step, shows the statute text each date was read from, exports a calendar file (.ics) and sends reminders 14, 7 and 1 day before each deadline. It tracks and reminds; it does not file anything for you.

Other states