Tennessee mechanics lien deadlines

3 deadlines NoticeGuard models for Tennessee: what each one counts from, the statute it was read from, and the statute text.

Information, not legal advice. This app reports what the statute says and cites the section it read. It is not legal advice, it does not file anything for you, and it does not tell you what to do.
Verify with the statute or an attorney. Statutes change, and courts reinterpret them. Every deadline in this app comes from a statute read on the date shown next to its citation - that snapshot can go out of date. Missing a mechanics lien deadline can extinguish your claim permanently, so confirm any deadline you are relying on with an attorney licensed in that state before you act on it.
Data verified: statute text retrieved 2026-09-21 (each citation below carries its own date). Rule data from the NoticeGuard app, source commit 22f9300.

Deadlines at a glance

DeadlineCounted fromApplies toStatute
Prime contractor's suit to enforce the lien365 days after final completion of the original contractOriginal contractorTenn. Code Ann. § 66-11-106 (sole sentence, "Duration of lien")
Notice of nonpayment (remote contractor)90 days after last furnishing (last day on site)Subcontractor, Supplier, Preconstruction service
only when you do not tick "This is a one-, two-, three-, or four-family residential improvement"
Tenn. Code Ann. § 66-11-145 (a)
Record sworn statement / serve notice of lien90 days after final completion of the original contractOriginal contractor, Subcontractor, Supplier, Preconstruction serviceTenn. Code Ann. §§ 66-11-112 and 66-11-115 112(a); 115(a)(2)

Work out a date for Tennessee with the calculator

Each deadline, with the statute

Prime contractor's suit to enforce the lien

Counted from completion or abandonment of the improvement. The lien continues to exist through final decision of any suit properly brought within this period.

What it counts from. 365 days after final completion of the original contract.

Applies to. Original contractor.

Tenn. Code Ann. § 66-11-106 (sole sentence, "Duration of lien")
Official source · statute text retrieved 2026-09-21

“A prime contractor's lien shall continue for one (1) year after the date the improvement is complete or is abandoned, and until the final decision of any suit properly brought within that time for its enforcement.”

If the date is missed (the statute's own terms). The statute states the lien "shall continue for one (1) year" and, if a suit is properly brought within that year, continues further "until the final decision" of that suit - a lien not enforced by suit within the year does not continue past it.

Also stated next to this deadline.

Notice of nonpayment (remote contractor)

Served on the owner and the prime contractor, counted from the last day of the month in which this claimant furnished labor, services, materials, or equipment and remains unpaid. Not owed on a one- to four-family residential improvement.

What it counts from. 90 days after last furnishing (last day on site).

Applies to. Subcontractor, Supplier, Preconstruction service (when you do not tick "This is a one-, two-, three-, or four-family residential improvement").

Tenn. Code Ann. § 66-11-145 (a)
Official source · statute text retrieved 2026-09-21

“Every remote contractor with respect to an improvement, except one-family, two-family, three-family and four-family residential units, shall serve, within ninety (90) days of the last day of each month within which work or labor was provided or materials, services, equipment, or machinery furnished and for which the remote contractor intends to claim a lien under this chapter, a notice of nonpayment for the work, labor, materials, services, machinery, or equipment to the owner and prime contractor in contractual privity with the remote contractor if its account is, in fact, unpaid.”

If the date is missed (the statute's own terms). The statute requires this notice as a condition for a remote contractor "to claim a lien under this chapter" for the unpaid work - the exact penalty for a missed notice was not independently confirmed from the primary source past "a remote contractor who fails to provide the notice... shall have no..." (see `limitations`); do not assume any specific consequence beyond what the statute itself was confirmed to say.

Also stated next to this deadline.

Record sworn statement / serve notice of lien

Recorded with the register of deeds (or, for a remote contractor, also served on the owner), counted from completion or abandonment of the improvement. For an original contractor this protects lien priority against later third-party purchasers only - it is NOT required as against the owner. For a subcontractor, supplier, or preconstruction service provider, the same act is a real precondition to having lien rights against the owner at all.

What it counts from. 90 days after final completion of the original contract.

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

Tenn. Code Ann. §§ 66-11-112 and 66-11-115 112(a); 115(a)(2)
Official source · statute text retrieved 2026-09-21

“[§ 66-11-112(a)] In order to preserve the priority of the lien provided by this chapter as of the date of its attachment, as concerns subsequent purchasers or encumbrancers for a valuable consideration without notice of the lien, though not as concerns the owner, the lienor... is required to record in the office of the register of deeds of the county where the real property... lies, a sworn statement of the amount for, and a reasonably certain description of the real property on, which the lien [is claimed]... Recordation is required to be done no later than ninety (90) days after the date the improvement is complete or is abandoned... [§ 66-11-115(a)] Every remote contractor shall have the lien provided by this part... provided, that the remote contractor: (1) Satisfies all of the requirements set forth in § 66-11-145, if applicable; and (2) Within the time provided for recording sworn statements set out in § 66-11-112(a), serves a notice of lien, in writing, on the owner of the property on which the improvement is being made.”

If the date is missed (the statute's own terms). For an original contractor, the statute itself says recording within this period is "not... as concerns the owner" - it protects priority against later third-party purchasers/encumbrancers only. For a subcontractor, supplier, or preconstruction service provider, § 66-11-115(a)(2) makes serving this notice on the owner, within the identical window, one of two express conditions (alongside § 66-11-145's monthly notice, "if applicable") for having a lien "provided by this part" at all.

Also stated next to this deadline.

Weekend and holiday rollover

NoticeGuard does not model a weekend or holiday extension for Tennessee. The dates above are the plain count from the date you enter. Check whether a Saturday, Sunday or holiday changes your date.