Vermont mechanics lien deadlines

2 deadlines NoticeGuard models for Vermont: what each one counts from, the statute it was read from, and the statute text.

Information, not legal advice. This app reports what the statute says and cites the section it read. It is not legal advice, it does not file anything for you, and it does not tell you what to do.
Verify with the statute or an attorney. Statutes change, and courts reinterpret them. Every deadline in this app comes from a statute read on the date shown next to its citation - that snapshot can go out of date. Missing a mechanics lien deadline can extinguish your claim permanently, so confirm any deadline you are relying on with an attorney licensed in that state before you act on it.
Data verified: statute text retrieved 2026-09-21 (each citation below carries its own date). Rule data from the NoticeGuard app, source commit 22f9300.

Deadlines at a glance

DeadlineCounted fromApplies toStatute
Record memorandum of lien180 days after payment due date (for the last labor or materials furnished)Original contractor, Subcontractor, Supplier, Preconstruction service9 V.S.A. § 1921 (c)
Commence action to enforce the lien180 days after notice of construction lien recordedOriginal contractor, Subcontractor, Supplier, Preconstruction service9 V.S.A. § 1924 (sole operative sentence)

Work out a date for Vermont with the calculator

Each deadline, with the statute

Record memorandum of lien

Filed with the clerk of the town where the real estate is situated, counted from the date payment became due for the last labor performed or materials furnished.

What it counts from. 180 days after payment due date (for the last labor or materials furnished).

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

9 V.S.A. § 1921 (c)
Official source · statute text retrieved 2026-09-21

“A lien herein provided for shall not continue in force for more than 180 days from the time when payment became due for the last of such labor performed or materials furnished unless a notice of such lien is filed in the office of the town clerk as hereinafter provided.”

If the date is missed (the statute's own terms). The statute's own mechanism: the lien "shall not continue in force for more than 180 days" from this date unless the memorandum is timely filed.

Also stated next to this deadline.

Commence action to enforce the lien

Counted from the date the memorandum of lien was filed - used when payment was already due at the time of filing.

What it counts from. 180 days after notice of construction lien recorded.

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

9 V.S.A. § 1924 (sole operative sentence)
Official source · statute text retrieved 2026-09-21

“Within 180 days from the time of filing such memorandum, if such payment is due at the time of such filing and within 180 days from the time such payment becomes due, if not due at the time of such filing, such person may commence his or her action for the same and cause such real estate or other property to be attached thereon.”

If the date is missed (the statute's own terms). The statute frames commencing the action within this period as what preserves the right to attach the property - the practical enforcement mechanism for the lien.

Also stated next to this deadline.

Weekend and holiday rollover

NoticeGuard does not model a weekend or holiday extension for Vermont. The dates above are the plain count from the date you enter. Check whether a Saturday, Sunday or holiday changes your date.

What this rule set does not cover

Keep track of the dates

About the NoticeGuard app

NoticeGuard is an app that turns a job's dates into a countdown for each statutory step, shows the statute text each date was read from, exports a calendar file (.ics) and sends reminders 14, 7 and 1 day before each deadline. It tracks and reminds; it does not file anything for you.