North Carolina mechanics lien deadlines

2 deadlines NoticeGuard models for North Carolina: what each one counts from, the statute it was read from, and the statute text.

Information, not legal advice. This app reports what the statute says and cites the section it read. It is not legal advice, it does not file anything for you, and it does not tell you what to do.
Verify with the statute or an attorney. Statutes change, and courts reinterpret them. Every deadline in this app comes from a statute read on the date shown next to its citation - that snapshot can go out of date. Missing a mechanics lien deadline can extinguish your claim permanently, so confirm any deadline you are relying on with an attorney licensed in that state before you act on it.
Data verified: statute text retrieved 2026-09-21 (each citation below carries its own date). Rule data from the NoticeGuard app, source commit 22f9300.

Deadlines at a glance

DeadlineCounted fromApplies toStatute
File claim of lien on real property120 days after last furnishing (last day on site)Original contractor, Subcontractor, Supplier, Preconstruction serviceN.C. Gen. Stat. § 44A-12 (b)
Commence an action to enforce the lien180 days after last furnishing (last day on site)Original contractor, Subcontractor, Supplier, Preconstruction serviceN.C. Gen. Stat. § 44A-13 (a)

Work out a date for North Carolina with the calculator

Each deadline, with the statute

File claim of lien on real property

Filed with the clerk of superior court, counted from this claimant's own last furnishing of labor or materials at the site of the improvement.

What it counts from. 120 days after last furnishing (last day on site).

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

N.C. Gen. Stat. § 44A-12 (b)
Official source · statute text retrieved 2026-09-21

“Claims of lien on real property may be filed at any time after the maturity of the obligation secured thereby but not later than 120 days after the last furnishing of labor or materials at the site of the improvement by the person claiming the lien.”

If the date is missed (the statute's own terms). A claim of lien not filed within this period is not filed in time - the statute states the outer bound plainly ("not later than 120 days").

Also stated next to this deadline.

Commence an action to enforce the lien

Counted from the SAME date the filing deadline uses - this claimant's own last furnishing of labor or materials - not from the date the claim of lien was actually filed.

What it counts from. 180 days after last furnishing (last day on site).

Applies to. Original contractor, Subcontractor, Supplier, Preconstruction service.

N.C. Gen. Stat. § 44A-13 (a)
Official source · statute text retrieved 2026-09-21

“No such action may be commenced later than 180 days after the last furnishing of labor or materials at the site of the improvement by the person claiming the claim of lien on real property.”

If the date is missed (the statute's own terms). The statute states the action "may [not] be commenced later than" this date - a strict outer bound, independent of when the lien itself was filed.

Also stated next to this deadline.

Weekend and holiday rollover

NoticeGuard does not model a weekend or holiday extension for North Carolina. The dates above are the plain count from the date you enter. Check whether a Saturday, Sunday or holiday changes your date.

What this rule set does not cover

Keep track of the dates

About the NoticeGuard app

NoticeGuard is an app that turns a job's dates into a countdown for each statutory step, shows the statute text each date was read from, exports a calendar file (.ics) and sends reminders 14, 7 and 1 day before each deadline. It tracks and reminds; it does not file anything for you.